10. Design the s/EAP budget

Summary

Latest update: 08/2025

This chapter will guide you through the s/EAP budget and provide guidance on how to fill the budget template. You will familiarize yourself with the eligible types of activities in an s/EAP, learn where to find the latest version of the budget template and receive tips and tricks on what to consider and how to fill the template.

Step 1: Familiarize yourself with the eligible types of activities in an s/EAP

The IFRC budget follows the IFRC plan and budget. This outlines the sector interventions that fall under the ‘planned operation’ and cross cutting ‘enabling approaches’.

The operational matrix in the s/EAP and the budget should correspond to each other. For example, if two trainings are planned under shelter, settlement and housing, then these trainings should be included under the same sector in the budget template.

Planned operations sectors and enabling approaches:

IFRC ‘planned operation’ sectors (11 in total)

  • Shelter, Settlement and Housing; Livelihoods; Multipurpose Cash; Health; WASH; Protection, Gender and Inclusion; Education; Migration; Risk Reduction; Community Engagement and Accountability; and Environmental Sustainability

IFRC Enabling approaches (3 in total)

  • Coordination and Partnership (activities for stakeholders external to the RCRC)
  • Secretariat Services (dedicated for IFRC activities)
  • National Society Development (dedicated for National Society activities)

Eligible types of activities in an s/EAP:

  • Readiness activities are any ongoing costs and services, including HR and logistics, that are necessary for the National Society to remain ready to activate and implement early action activities These costs should be spread out annually over the five-year lifespan of an EAP or two-year lifespan for an sEAP.
  • Prepositioning activities, enables National Societies to procure and preposition the stock required for early action, so it is available once a trigger is reached. The stock should have a shelf-life of two years or five years, aligned with the respective lifespan of an s/EAP. The budget can include related costs such as warehousing, transportation and insurance. Note that stock that has a shelf life shorter than five years / two years such as nutrition, pharmaceuticals and medical items may not be eligible for prepositioning. As an alternative,  National Society’s should identify suppliers who can supply these items within the lead time.
  • Early action activities are activities that are done to reduce or mitigate the impact of a hazard on at risk communities. Early action activities should be completed within the lead time; however, some expenditures will be eligible and follow up cost may be incurred after the end of the early action lead time (e.g. debriefing volunteers, monitoring activities, lessons learned workshop). These activities need to be completed within the operational timeframe, normally three months after the activation.

Examples of the operational matrix from the EAP template

Examples of the operational matrix from the EAP template

  • Planned operation sector: Shelter, Settlement and Housing

  • Planned operation sector: Livelihoods

  • Enabling approach: Coordination and partnership

Step 2: Download the latest version of the template

Before you get started preparing your budget, make sure that you have the latest version of the budget template (the latest template is dated 2025). You can pick the budget template directly from FedNet or from the IFRC delegation.

Step 3: Plan the budget and fill the budget template

Before you start inputting the budget – make sure you select the protocol type in cell K5 – from the drop down menu, select either Standard EAP or Simplified EAP.  This will automatically set the budget caps and will alert you if the budget cap is overspent.

Budget caps for EAPs and sEAPs:

The maximum budget for a full EAP is CHF 900,000. The maximum budget for a simplified EAP is CHF 200,000. These figures must be inclusive of the IFRC indirect or programmes and services support recovery (PSSR) of 6.5 per cent.

The IFRC delegation supporting the National Society can add 20,000 for a simplified EAP or CHF 50,000 to support the maintenance and activation of an s/EAP. This sum must include the 6.5 per cent IFRC indirect or programmes and service support recovery (PSSR). The National Society and the IFRC should use the same budget template.

When filling out the budget template, most cells can be copy and paste, except for four columns, where options must be selected manually from the drop down menu:

  • In column C: use the dropdown menu to indicate the type of activity: readiness, prestock or early action.
  • In column D: use the dropdown menu to indicate who will be implementing the activity: Host NS, IFRC or PNS, if a partner has a role in the s/EAP.
  • In column E: use the dropdown menu to indicate when the activity will be done:
    For readiness, indicate which year the activity will be done (YEAR 1 – YEAR 5 – for a full EAP or YEAR 1 – YEAR 2 – for a simplified EAP. If you don’t see these options in the drop down menu – make sure that you have selected the correct protocol type, cell K5, ‘standard EAP’ or ‘simplified EAP’). If the activity is done 5 times, you will need to copy this column five times and allocate the five to ‘YEAR 1’, ‘YEAR 2’, through to ‘YEAR 5’. Note, you cannot budget the activity for five years in just one line.
    For prepositioned stock
    , under the simplified EAPs, stock is always budgeted in ‘YEAR 1’. For a full EAP, stock should be budgeted twice, one allocation in ‘YEAR 1’ and ‘YEAR 5’. Following the first activation, the second allocation will be transferred, so that the stock can be procured and prepositioned in advance of a second activation.
    For early actions, should be budgeted under ‘Trigger 1’ for the sEAP and for a full EAP, the first activation is budgeted under ‘Trigger 1’ and ‘Trigger 2’ for the second activation.
  • In column F: indicate using the dropdown menu the appropriate budget group. The full list of budget groups can be found under the excel tab called ‘budget group’.

 

Top Tips: 

  • Make sure that you save the template as a .xlsm (macro enabled workbook).
  • Make sure that you select the correct budget type, cell 5K, standard EAP or simplified EAP.
  • For columns C to F, use the dropdown menu – you cannot copy and paste into these cells.
  • Make sure that all AP codes and budget groups are filled for each column, otherwise the other tabs will not calculate correctly.
  • An example of a completed budget template can be found in the toolbox.

If the budget tool is completed correctly, then the spreadsheet tabs will automatically calculate:

  • EAP BUDGET FOR PUBLISHING, which groups the budget by planned operation and enabling approaches.
  • SUMMARY BY AP CODE, which gives a breakdown by planned operation and enabling approaches, broken down by readiness, preposition stock and early action.
  • SUMMARY BY YEAR, which provides a breakdown of amount and percent of readiness, prepositioned stock and early action by Host National Society, the Partner National Society (if applicable) and the IFRC, by year. You will also receive alerts, if the budget caps are exceeded, or activities have been budgeted incorrectly. Note for IFRC staff, this tab can be used when populating the IFRC project agreement.
  • RESOURCE BUDGET SUMMARY, which provides a more detailed breakdown by AP code across readiness, prepositioned stock and early action.
  • BUDGET GROUP, here is the list of budget group codes which can be used to populate the budget tool, column F.
  • WBS, this tab summarises the budget by implementing party and ouput to allow the IFRC-DREF Operations Project Manager an easy reconversion of the data into IFRC’s D365 system.
  • GUIDANCE, this tab provides additional guidance on how to complete the budget. We recommend that you consult this tab before you start working on the budget template.

Step 4: Double-check what goes where

What goes where?

  • As much as possible, ensure that activities are included in the appropriate sector under the planned operation. For example, if there is a general training which will cover Shelter, Health and PGI – rather than including a lump sum under ‘National Society Strengthening’, pro rata the costs under the relevant sectors – 33 per cent allocated to shelter, 33 per cent allocated to health, and 34 per cent allocated to PGI.
  • Any costs related to the IFRC, should be included under ‘Secretariat Services’.
  • Any costs related to the National Society which cannot be attributed to a sector, or are related to National Society running costs, should be included under ‘National Society Strengthening’.
  • Volunteer insurance should be budgeted under ‘National Society Strengthening’.
  • Early warning and evacuation should go under ‘Risk Reduction’.
  • Household items (mattresses, blankets, kitchen sets, etc.) should be planned and budgeted under ‘Shelter, Settlement and Housing’.
  • The lessons learned workshop should normally be included under ‘National Society Strengthening’, always as an early action (YEAR EA).
  • Any coordination with stakeholders whether the Met Service or Government departments, whether readiness, stock or early action should be included under ‘Coordination and Partnerships’.
  • PDM related to health should be included under the health sector, however general CEA such as a community feedback mechanism should be included under ‘Community Engagement and Accountability’.
  • The IFRC indirect costs, or PSSR, is automatically calculated as part of the budget template.

Step 5: Double-check that your budget meets all the guidelines

Before you complete your budget, make sure that it meets all the guidelines:

  • Maximum 65 per cent of the total budget can be allocated for readiness activities and prepositioned activities combined. It is up to National Societies to decide how to allocate the budget over these two types of costs. National Societies that request a high proportion of readiness costs (more than 35per cent) may be requested to justify the allocation. Also, National Societies who have more than one EAP may be requested to demonstrate that readiness costs are diminishing.
  • The National Society may include administrative costs of up to 5 per cent of the total budget. If the 5 per cent rate is not used, the National Society will need to list out each administrative cost individually generated during the early action phase (finance, logistics, electricity, support staff, etc.)
  • The monitoring and evaluation budget should be maximum 5 per cent of overall the budget (CHF 47,500 maximum for a full EAP or CHF 10,000 maximum for an sEAP).

Tip: If you need assistance with preparing your budget, reach out to your IFRC Delegation Financial Focal Point.